Hotel Construction Schedule

6 replies [Last post]
Susa Kamanusa
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 24 Sep 2006
Posts: 6
Groups: None

Hi all,

I'm new to this forum and I'm looking forward to being a contributing member. I just got assigned to create a project for a small hotel and would your help. Can anyone send me a sample schedule they did so I can compare mine?

If so send to : hijazem@yahoo.com

thank you...

Replies

Susa Kamanusa
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 24 Sep 2006
Posts: 6
Groups: None

Dear Ulysses and all,

I registered back in 24-9-2006, but following that in a short time I left the planning field for a while; however, I recently back and active on the planning scene and plan on being an active member.

Thanks for your inquiry

Susa Kamanusa
User offline. Last seen 14 years 32 weeks ago. Offline
Joined: 24 Sep 2006
Posts: 6
Groups: None

Thanks Rory for the reply,

Even though I registrered back in 2004 I have never used the forum since then; however, I recently active on the planning scene and plan on being an active member.

Thanks

Rory Hoban
User offline. Last seen 4 years 43 weeks ago. Offline
Joined: 27 Jan 2011
Posts: 10

May have joined pp in 2006 but susa only states "NEW TO THIS FORUM"

Not sure why you need to highlight this twice

 

Hi SUSA

I am also new to this forum - spend most of my time on LinkedIn

Back to your question - Hotel programme (ask yourself)

- 1st The sq.m size hotel ie basement construction, number of bedrooms, Kitchen, dining area, bars admin, reception

- 2nd contract or target programme

- 3rd How are you going to services this project ie tower / mobile cranes, teleporters, conc pumps / conc tower booms

 

My hotel Contract programme would look something like:

- Substructure

- super structure

- Roofing

- Envelope

- Building seal date

- Plantroom Structure / lift over run

 

Internal Finishes

- Back of house

- front of house

- Bedrooms ( would not break out floor by floor for contract)

- basement finishes

- lift installation

- plantroom installation

- Is FF&E part of your contract

 

External Works

- FW & SW drainage

- watermains

- site services

- landscape areas

- Roads / Paths / Signage

 

Hope this of use to yourself

Jehad Aldaoud PMP...
User offline. Last seen 5 years 45 weeks ago. Offline
Joined: 8 Oct 2010
Posts: 57
Groups: None

You can use the sample projects from Primavera program 

 

best regards 

ulysses garcia
User offline. Last seen 14 years 35 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar

You are a member since 2006-09-24

ulysses garcia
User offline. Last seen 14 years 35 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar

You are a member since 2006-09-24