hotel planning

6 replies [Last post]
Rola Sabbah
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
hi every body
i’m planning a hotel righ now, can somebody send me a time schedule to compare with mine, and have some ideas its a challenging job.
thanx

Replies

yasir arafath
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 17 Jan 2011
Posts: 5

Dear samer,

                As i am new to planning field , I am not aware of Building Plan and their activities ,

So it would be very helpful if you send me  sample copy of  Building plan or hotel project and their activities details.

My id : yasirlinks@yahoo.com

Thanks and regards. 

Yasir arafath 

Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Rola,

I also recommend that you have the Roof and the Ground Floor Lobby and other service areas underseparate headings. You can start out by having a list of the rooms at each floor, then you proceed with listing the activities needed for each room.

With kind regards,

Samer
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Rola,

Let us start after skeleton and you can repeat the activities for each floor:

I. Rooms
Block Building
Door subframes
Platering Guides
1st fix EM installation in walls
Electrical:
Lighting
Power
Low Current
Mechanical
HVAC
Fire Fighting
Plastering 2nd and 3rd layers
1st fix under tiles
2nd fix EM under tiles
Tiling
Skirting
Gypsum Board in Ceiling
EM Openings in Gypsum Board in Ceilings
Window Threshold installation
Aluminum works
Painting 1st layer
Painting 2nd layer
Front Door installation
Carpeting
Wood Works substructure
Wood Works finishings
3rd fix in wood
Final Paint
Curtains
Paintings
Loose Furniture
Commissioning
II. Rooms Bathroom
Block Work
Subframe installation
Cistern Installation
Mechanical
HVAC
Plumbing
Plastering Guides
1st fix EM
Plastering 2nd layer
EM works about False Ceiling
False Ceiling
Tiling walls
Floor insulation
Floor insulation protection
Tiling Floors
Door installation
Sanitary Fixtures installation
Mirrors installation
EM 3rd fix in walls
EM 3rd fix in Ceiling
Toliet Accessories installation
Final Paint touch up

III. Rooms Balcony
Walls Platering Guides
Mechanical Drainage
Electrical 1st fix
Walls Plastering 2nd and 3d layer
Tiling
Parapet threshold installation
Handrail installation
Handrail Paint (if any)
External walls and ceiling paint
Electrical 3rd fix

IV. Corridors
Something similar to the above.
You can add:
Service areas at each floor
Lift Lobby works
Stair Cases

Of course all the above is general information, you need to read your BOQ and drawings in order to be more specific. If you need more details, please let us know.

With kind regards,

Samer
Rola Sabbah
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
hi
thank you for your help.
im planning a hotel of 19 floor , including 3 basements, and a roof that contains a spa and a jim.
the skeleten is ready, i have to plan the block, EM, Finishes, the external finishes includes, glass, stone,and paints.
if any body can help me and send me a copy of a hotel plan.
the problem is the finishes sequence, carpet and finishes, sanitary and risers
thanx
asd salim
User offline. Last seen 6 years 18 weeks ago. Offline
Joined: 17 Jan 2007
Posts: 6
dear rola
im ready to help u..just giv me more ideas about ur project
regards
salim
Samer Zawaydeh
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Rola,

Each project is unique, so most probably, having a copy will not assist you.

Give us a small description of the project that you are working on and we can assist you more.

With kind regards,

Samer