Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Timber Frame Construction

4 replies [Last post]
James Young
User offline. Last seen 12 years 50 weeks ago. Offline
Joined: 13 Jun 2008
Posts: 71
Groups: None
Hi all,
does anyone know the sequence of events when construction a Timber Framed building?

Regards,

J

Replies

Sham Dham
User offline. Last seen 10 years 32 weeks ago. Offline
Joined: 7 Mar 2011
Posts: 2
Groups: None

Has anyone done a study on installation rates for Cross Laminated Timber type of buildings

And how much faster it is compared to tradinal build

Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear James,

The typical activities are :

1) Substructure
a. Excavation
b. Foundation
c. Foundation Insulation and Insulation Protection
d. Fill
e. Slab on grade
2) Superstructure
a. Main Frames
b. Secondary Beams and Bracings
c. Cladding
d. Door and Windows
e. Gutters and Downspouts.
3) Electromechanical Works
4) Finishes

With kind regards,

Samer
Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi James

The usual sequence is.

1. Fix and Level sole plates
2. Install wall panels - line and level
3. Fix floor cassettes
Repeat 2 & 3 up to roof plate
4. Fix roof plate
5. Fix roof trusses.

Best regards

Mike Testro
John Banks
User offline. Last seen 4 years 41 weeks ago. Offline
Joined: 28 Jun 2007
Posts: 35
I’ve got some MSP examples for residential timber kit if that’s any use?