Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Timber Frame Construction

1 reply [Last post]
Paul Robinson
User offline. Last seen 5 years 24 weeks ago. Offline
Joined: 27 May 2004
Posts: 5
Groups: None
Everyone

I have in my past undertaken timber frame building but only once have I done a steel frame with timber infill panels.

The one time I did the conrtactor let the company down badly and instead of achieving programem they caused a delay of approx 2 months.

Has any one done the infill panel construction and do you have an idea of rpoduction rates.

Thanks

Paul


Replies

John Lawson
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 6 Oct 2004
Posts: 113
Hi,

Sounds like you had a contractor that had other problems than just knocking this building together. Most firm that do this sort of work are pretty well organised, have done it so many times and don’t cause to many problems.

For rates all depends on the complexity of the structure, but for a "bog" standard job, try using 60-70 manhours a tonne for the prefabication work. Onto which add(?) a value for the surface protection i.e blasting/painting/galv.

For Erection of the main Structure try 20-30 manhours a tonne, again all depends on complexity of structure. For items such as supports, handrails try 200 manhours a tonne. This would be for a bolted stucture.

What I normally do is work out the tonnage (approx), apply the rates, this gives me my manhours for the job. I then assume a resonable crew size/mix i.e. couple of riggers/slingers, couple of steel erectors and a crane Driver and then calculate the duration for the work.

If it "feels" ok, i.e. would I like to be doing the job in that time I will use this estimate, if not I move up the rates etc., its that old "gut feel" thing.

Regards

John