concrete frame rates

1 reply [Last post]
KONESH SRIDARAN
User offline. Last seen 17 years 24 weeks ago. Offline
Joined: 5 Sep 2006
Posts: 7
Groups: None
Hellow Guys,

Working on a concrete frame pre-quaification programme 7 stories. just to get a quick cross check .What is the rate of construction for 1100 (138m X 8m) msq with 38 columns (300 X300m cols) 225mm thick deck.

Thanks

Konesh

Replies

Brij Patwari
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 28 Aug 2004
Posts: 13
Groups: None
Can any body guide, how to assume resource staturation??
I am working on a project where manpower is not a constraints.. Its about resource saturation??
Can anybody, from their experience tell how can i link Space with 1 man so that i can know how many max no of manpower can be deployed??