Resource usage spreadsheet

1 reply [Last post]
Mahmoud mohamed
User offline. Last seen 13 years 21 weeks ago. Offline
Joined: 15 Jun 2008
Posts: 4
Groups: None
Hi
In P6 the resource usage spreadsheet show me the resource’s quantities distributed within the activity duration – I need to show the data as percentage within the duration

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mahmoud,

You can do this by using the spreadsheet option --> Calculate Average.

Example: Total qty of your manhour is 20,000 hrs. divide the total qty by 100 which is equals to 200.

Write the 200 in "Divide interval totals by" & under the "Unit of Measure" put the % symbol.

Try this exercise.