Productivity Rate

4 replies [Last post]
Frans Lasut
User offline. Last seen 15 years 28 weeks ago. Offline
Joined: 13 Jun 2006
Posts: 26
Dear all

1. How to best calculate productivity rate of a construction activity?

2. Why there is no productivity rate column in P3 or MSP?

Ragards
frans

Replies

Shah. HB
User offline. Last seen 19 weeks 2 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773
Productivity rate = [Work quantity/{activity duration * resource usage}]
Productivity may be measured as the quantity of work per one hour, or as quantity of work hourd per one unit of work quantity.

Best Regards,
Vladimir
Mohammed Mujtaba
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 23
Can any one tell the specific formula for calculating productivity.
Frans,
if you want to use productivities in schedule development try Spider Project (Demo can be downloaded from http://www.spiderproject.ru/spider_e.php).
In this package you can assign productivities manually or create Productivity database and use it in all projects of the organization.
I don’t know why work quantities and resource productivities are not supported by other software packages.
Regards,
Vladimir