effort

1 reply [Last post]
Rola Sabbah
User offline. Last seen 10 years 27 weeks ago. Offline
Joined: 5 Dec 2009
Posts: 61
what is the way of calculating effort?
is it by resources hours spent on the activity? or is there another way?

Replies

Rodel Marasigan
User offline. Last seen 10 hours 36 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Rola,
It depends on your settings and type of activity. If physical then should be by production step or measured items, Time or duration if task is measurable by time and units if resource driving activity.