Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Resources

4 replies [Last post]
Randy Taylor
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 2 Mar 2009
Posts: 7
Under Enterprise Resources,(for resource loading)I have set my Price/Unit category to calculate my internal cost per unit and have dedicated Price/Unit2 category as my revenue for billing.
Going back to the Activites View, can I replace the unit/price cost catagory with the unit/price2 revenue catagory. If so please advise how.

Replies

Randy Taylor
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 2 Mar 2009
Posts: 7
Thanks Karim, that was the piece I was missing. It’s working great!
Karim Mahgob
User offline. Last seen 6 years 15 weeks ago. Offline
Joined: 11 Feb 2009
Posts: 9
This column you can find it in the resouce assigment window go to columns and select a column called (Rate Type)....for each assignment you’ll choose the rate type for it
Randy Taylor
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 2 Mar 2009
Posts: 7
I had wondered the same thing earlier and had tried that but found that the unit/price2 column doesn’t exist in any of the options and can only be viewed if I start at the Enterprise level and step into the Resources.
Still struggling.
David Maguire
User offline. Last seen 7 years 5 weeks ago. Offline
Joined: 11 Sep 2007
Posts: 3
Groups: None
Can it not just be replaced through right clicking on the Activities & selecting columns and editing them?

Regards

Maguire