Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Project and Construction Planner, Downer Edi Engineering, Curragh Mine CHPP Expansion Project, Wesfarmers Resources

START Date: 
March, 2008
END Date: 
May, 2011
  • Supported delivery of a new Coal Preparation Plan for Wesfarmers at Curragh Mine in Blackwater ($300m). Responsibilities included:
    • Responsible for weekly progress updating of comprehensive EPCM project schedule
    • Prepared work breakdown structure for EPCM contract
    • Ensuring baseline management and control measures were in place
    • Schedule maintenance and weekly updating and reporting
    • Vendor and project status reporting including variance analysis, manning histograms and s-curves
    • Developed a detailed construction program outside the constraints of the program being utilised by the project to better manage construction progress at a detailed level
    • Baseline management
Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000