How to show Baseline 2 Duration column in primavera

2 replies [Last post]
Antony Magesh
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 15 Dec 2013
Posts: 2
Groups: None

I am Comparing Initial Stage Baseline Schedule (Baseline 1) with Management Sign off baseline (Baseline 2) in Primavera.

Can anyone advise me how to show Baseline 2 Duration column in primavera.

Replies

Jerome Odeh
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 19 Jan 2004
Posts: 102

Antony,

Have you tried to add a BL2 Duration UDF of data type Number or Integer and then apply a Global Change (BL2 Finish - BL2 Start) to calculate your BL2 Duration?

Downside of this workaround is that your WBS BL2 Duration will be wrong since UDF of Number/Integer types are summed.

=jerome
PlannersPlace.com

Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

P6 can't show BL2 Durations, only BL1.

 

Project Baseline is the baseline project that all users see when they open the project. BL1 and BL2 are specific to each user and the fields that P6 calculates for BL1 and BL2 is not as extensive as for Project Baseline.