Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Color Activity not meeting Baseline

1 reply [Last post]
Jithin Kambhikanam
User offline. Last seen 3 weeks 2 days ago. Offline

Hello Everyone,

 

Is there a way by which the Activity Bar which didnt meet the Basline Date can be highlighted in a different colour Say like Orange.

 

Red coloured bar is critical activity, but I would like to show activities which hasnt met the baseline date in Yellow.

 

Any chance ?

 

Thanks

Jithin

Replies