Budgeted Labor Units

1 reply [Last post]
Vrinda M
User offline. Last seen 1 week 1 day ago. Offline
Joined: 8 Jun 2008
Posts: 23

Dear all,

I have hammock activity Boundary wall works with no budgeted labor units  assigned to that activity.

But after updating programme this activity showing Planned Value labor Units and Earned Value Labor Units 4312 & 5778. Please advise why it showing these units automatically 

After i export this programme to another users, tse units/values are not seen. Please advise.

 

Rgds,

Vrinda.

 

 

 

Replies

Zoltan Palffy
User offline. Last seen 18 hours 24 min ago. Offline
Joined: 13 Jul 2009
Posts: 1896

it is simply summarizing the units of the activites that the LOE is summarizing.