Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Budgeted Labor Units

1 reply [Last post]
Vrinda M
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 8 Jun 2008
Posts: 24

Dear all,

I have hammock activity Boundary wall works with no budgeted labor units  assigned to that activity.

But after updating programme this activity showing Planned Value labor Units and Earned Value Labor Units 4312 & 5778. Please advise why it showing these units automatically 

After i export this programme to another users, tse units/values are not seen. Please advise.

 

Rgds,

Vrinda.

 

 

 

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

it is simply summarizing the units of the activites that the LOE is summarizing.