Manpower Budgeted Time is Changing

3 replies [Last post]
Suhaib Nassar
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 25 Jun 2018
Posts: 10
Groups: None

Dear all,

The manpower budgeted time of most of the activities keep changing over and over which also change the overall budgeted time in the resource assignment. Is there any ability to make them fixed as I built them in the beginning of the project?

Suhaib

Replies

Zoltan Palffy
User offline. Last seen 2 days 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1981

glad I could help

Suhaib Nassar
User offline. Last seen 6 weeks 1 day ago. Offline
Joined: 25 Jun 2018
Posts: 10
Groups: None

Many thanks Mr. Zoltan

Zoltan Palffy
User offline. Last seen 2 days 15 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1981

change duration type to fixed duration and units/time