Forum Sponsor:

Oracle Construction and Engineering (formerly Primavera) is transforming the world by helping organizations plan, build, and operate critical assets with on-premise and cloud-based project portfolio management solutions.  Learn more about Oracle Construction and Engineering...

We wish a warm welcome to the find people who are offering the ScheduleReader™ application. We hope to add more interesting news here shortly.

Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Manpower Budgeted Time is Changing

3 replies [Last post]
Suhaib Nassar
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 25 Jun 2018
Posts: 13
Groups: None

Dear all,

The manpower budgeted time of most of the activities keep changing over and over which also change the overall budgeted time in the resource assignment. Is there any ability to make them fixed as I built them in the beginning of the project?

Suhaib

Replies

Zoltan Palffy
User offline. Last seen 13 hours 14 min ago. Offline
Joined: 13 Jul 2009
Posts: 2102

glad I could help

Suhaib Nassar
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 25 Jun 2018
Posts: 13
Groups: None

Many thanks Mr. Zoltan

Zoltan Palffy
User offline. Last seen 13 hours 14 min ago. Offline
Joined: 13 Jul 2009
Posts: 2102

change duration type to fixed duration and units/time