Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Open a program in p6.4 with a release p6.3

1 reply [Last post]
Ant Pir
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 17 Jun 2013
Posts: 11
Groups: None

Hi,

Somone kow the procedure how open a program saved p6.4  with  a release p6.3

Regards

Replies

Zoltan Palffy
User offline. Last seen 6 weeks 9 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to windows explorer

highlight the xer file 

right click and select open with then choose note pad or word pad

in the first line of the file chnage the numbers from 6.4 to 6.3

save file

import file