at completion duration issue

1 reply [Last post]
umit timu
User offline. Last seen 7 years 21 weeks ago. Offline
Joined: 17 Apr 2016
Posts: 2
Groups: None

Hi Folks

Im importing same xer file into enterprise and into standalone version of p6

Im getting different dates&floats when scheduling with retained logic

 

when investigating reason, i saw that at completion durations are different for some in-progress activities , but all settings are same on both platform. I couldnt find out why

 

Any ideas?

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

2 possibilities 

1. go to edit users preference look a the time units and look at the Hours per Time Period.

2. it is using the gloabl calendar instead of a project calendar and the two global calendars are different.