Reducing budgeted labor units by 10% for a large number of tasks

2 replies [Last post]
Jean Desjardins
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Hi everyone,

Does anybody know how to reduce the budgeted labor units by 10% for a large number of tasks in P6 ?

I tried using global change but did not find budgeted labor units in the drop menu.

Thanks

Replies

Jean Desjardins
User offline. Last seen 9 years 27 weeks ago. Offline
Joined: 7 Nov 2011
Posts: 23
Groups: None

Thank you Raymund

Raymund de Laza
User offline. Last seen 40 weeks 3 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

On the Global Change.. in Subject Area select Activity Resource Assigngment...