P3e - How can you jump to a specific numbered task?

3 replies [Last post]
David Podmore
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
I’ve just been asked "how do you jump to a specific task number?" - Do you know, I don’t have a clue!
I can’t believe I’ve never wanted to, but there you go.

Is there a facility/F-key or some such to enter a task number (say A1230) and to jump straight to it just like you can in assigning relationships?

Replies

Arthur Godbeer
User offline. Last seen 14 years 40 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
Of course that method applies to any column, not only the Activity Id.
David Podmore
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 26 Apr 2006
Posts: 74
Groups: None
How simple is that?

Cool! Thanx
Arthur Godbeer
User offline. Last seen 14 years 40 weeks ago. Offline
Joined: 24 Jul 2006
Posts: 127
Groups: None
When you’re in that column, Edit/Find or Ctrl+F.