Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

New to Delay Analysis—Seeking Immediate Guidance, Please

No replies
Md Sakib Islam
User offline. Last seen 1 year 1 week ago. Offline
Joined: 22 Aug 2015
Posts: 9

Greetings to everyone

Hi

I am currently working on a delay analysis, and to be very honest, this is my first time tackling such a task. I am feeling quite stuck and could really need some help. I would be incredibly grateful if anyone could offer me some advice or pointers.
Here in UAE, we noticed a delay, during Ramadan time.our time has reduced from 8 hours a day to 6 hours a day. but we were getting work permit only for 3 hours a day.
So how can I estimate in Primavera that which activity is getting affected by this and by how much duration it is getting affected. Please help.

Zoltan Palffy
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3090
Groups: None

get your hands on the 52R-06 Time impact alanysis - as applied in construction 

this is a best practiice material that shows you how to do it 

this is by the aace which is the Association for the Advancement of Cost Engineering

 

Renzo Constenla B...
User offline. Last seen 3 weeks 1 hour ago. Offline
Joined: 23 Mar 2011
Posts: 21

Hello

 

the solution is that mentioned by Mr. Kelly.

Just to indicate that this problematic (time deviation, delay analysis, extension of time, etc) related to  forensic analysis is very interesting in planning/scheduling. There are several approaches to time impact analysis. Try with AACE recommended practices (among others).

Regards

david kelly
User offline. Last seen 6 hours 45 min ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Take a baseline.

Annotate all of the activities, perhaps with a code value, that have had their working day reduced to 3 hours

Run a Global Change, which alters the calendar of those activities to three hours per day

Reschedule

Baseline reports will show deviations cuased by the reduction of working hours

david kelly
User offline. Last seen 6 hours 45 min ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Take a baseline.

Annotate all of the activities, perhaps with a code value, that have had their working day reduced to 3 hours

Run a Global Change, which alters the calendar of those activities to three hours per day

Reschedule

Baseline reports will show deviations cuased by the reduction of working hours