I am currently working on a delay analysis, and to be very honest, this is my first time tackling such a task. I am feeling quite stuck and could really need some help. I would be incredibly grateful if anyone could offer me some advice or pointers.
Here in UAE, we noticed a delay, during Ramadan time.our time has reduced from 8 hours a day to 6 hours a day. but we were getting work permit only for 3 hours a day.
So how can I estimate in Primavera that which activity is getting affected by this and by how much duration it is getting affected. Please help.