Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Sequencing and Relationships guidance

4 replies [Last post]
adab azeez
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
I have 24 different equipment (3 columns, 10 exchanger, 11 drums) for maintenance. The date and Month of maintenance is not decided yet. And Schedule should be in such a way that, once the Project start date is changed all the maintenance dates have to change accordingly. All equipments can be started at the same day, but due to lack of manpower I have to create a proper sequence for maintenance in primavera. Either by using constraint or by using relationships with lags. What is the Standard Practice out of the following 3 for creating maintenance sequence ? 1. Create a start milestone and link each equipment's first activity with it, keeping some lags. 2. Use Primary constraint "start on" for each equipment's first activity to start maintenance at separate dates. 3. First equipment linked to start milestones and other equipments will be linked without any functionality.

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad we could help 

adab azeez
User offline. Last seen 2 years 17 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Thank you guys...Your ideas gave me new ways to explore.
Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

#1 is perfered the less constraints the better. 

Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
I may suggest none of the above. Just use the Data Date to run the schedule. Do not define any links and or constraints on your activities or equipment. However, you need to define and assign your exact resources to your activities, considering calendars, working and non-working hours, shifts (if any), and quantities. Try to run automatic resource leveling and see what happens. And please tell me if this helps. Oh, don't forget that your activities are resource-driven.