Help with Schedule Finish Dates

1 reply [Last post]
Stephen Van Ogle
User offline. Last seen 15 years 14 weeks ago. Offline
Joined: 21 Jan 2009
Posts: 3
Groups: None
In OPP for some reasn the Schedule Finish Dates are not matching the Actual Finish Dates. Activity is progressed and completed. Actual Finish Date is filled out and the task marked as Complete. There is 0 Remaining Effort. When I move the Time Now date forward, the Schedule Finish Dates move with it (Actual Finish Date stays the same). This is posing a problem since I have calculated fields that are based on the Scheduled Finish Column.

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline
I don’t have the software no this computer, so donig this from memory:

On the time now advanced settings, there should be an option called something like "actual dates overide logic". If that option isn’t enabled, I think out of sequence progress can cause issues like you describe.

HTH