project finish date

3 replies [Last post]
Sunil Babu
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi friends,

I have finish constraint for my project eg: must finish on or before

12-dec-2012 and I scheduled my project but the project showing the

finish date as 16-feb 2013 why it is happening like this...

your expert advice highly appreciated..

Regards.

Sunil

Replies

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

...but if the date was showing 16th feb with the fniish on or before constraint, this is becuase your schedule is telling you it is impossible to finish by 12th dec.

Making it a mandatory constraint will make the end date change, but it doesn't mean you will achieve that end date.

 

Really, you're just hiding the problem, rather than adressing it.

This is why I do not like mandatory constraints.

Sunil Babu
User offline. Last seen 4 years 36 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi Limson,

Thanks for your reply

Regards

Sunil

Daniel Limson
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Hi Sunil,

If you dont want your end date to move, used "Mandatory Finish"

Cheers,

Daniel