I have 2 projects open with 2 different data dates.

3 replies [Last post]
John Reeves
User offline. Last seen 23 hours 51 min ago. Offline
Joined: 10 May 2013
Posts: 286
Groups: None

I have 2 projects open with 2 different data dates.  I am sliding a bar in the 2nd one but my Duration at completion is not coming out right - or to fix that the dates are not correct.  I have checked the calendars - could it be because of the data dates?  I don't see what that has to do with it but I don't know what else it could be.  I tried it actualized in the future and un-actualized.  mystery...it is not off by the difference in data dates....

Replies

John Reeves
User offline. Last seen 23 hours 51 min ago. Offline
Joined: 10 May 2013
Posts: 286
Groups: None

I think the issue must have something to do with the Calendar "days" actually being hours -  the cal. came from a contractor so not yet about it, but I sustpect.  My 256 days slid 6 months does not match the dates of these 256 days later - per outside checks...

John Reeves
User offline. Last seen 23 hours 51 min ago. Offline
Joined: 10 May 2013
Posts: 286
Groups: None

I think the issue must have something to do with the Calendar "days" actually being hours -  the cal. came from a contractor so not yet about it, but I sustpect.  My 256 days slid 6 months does not match the dates of these 256 days later - per outside checks...

John Reeves
User offline. Last seen 23 hours 51 min ago. Offline
Joined: 10 May 2013
Posts: 286
Groups: None

I think the issue must have something to do with the Calendar "days" actually being hours -  the cal. came from a contractor so not yet about it, but I sustpect.  My 256 days slid 6 months does not match the dates of these 256 days later - per outside checks...