The software I use is different but maybe a similar approach will do the trick if using P6.
If you are looking to control maximum available units at the project level as well as the global level then a workaround might be to create a dummy resource with the desired maximum at the job level. Then assign the dummy resource the same quantity to every team the global resource is assigned.
I used P6 years ago but not any longer. If I am not wrong you specify individual values on the resource assignments tab. Make sure you make visible the column on the assignments tab so that you can edit the value.
If you are looking to control maximum available units at the project level as well as the global level then a workaround might be to create a dummy resource with the desired maximum at the job level. Then assign the dummy resource the same quantity to every team the global resource is assigned.
I would add a separate resource with a location identifier then allocate the Max Units/Time that way - e.g. Mechanic-Platform, Mechanic-Barge.
This will also allow you to set different calendars if required, which would also allow you the option of having a different calendar for the barge / work boat to take weather delay's into account.
Each project can then be scheduled independantly, or you can create a stacked histogram to see the combined resource hours for the same trade (or select the multiple trades in the resource profile).
This also allows you to identify the number of personnel on each site (for POB allocation if Offshore), as this is usually the limiting factor in the schedule. Again, the resource profile view will help with this.
We use Primavera EPPM for multiple assets offshore & all resources are set up with a location identifier to allow for the change in Units/Time.
If going this route, it is best to set up a Parent Resource of the Location to allow all the Site Specific resources to be added with the location as the Parent Resource - makes it easier when assigning in the plan.
If you are going to have to change the resource codes that are assigned on each location, then use a global change for each project / location to set the new Resource Code.
If you are using the Resource Leveling within Primavera, then you can then select only the resources you want to be leveled.
Member for
21 years 7 monthsThe software I use is
The software I use is different but maybe a similar approach will do the trick if using P6.
Please click following link for sample schedule.
http://www.mediafire.com/file/1aa8wrwgt13urbz/How_to_schedule_multiple_project_together_that_have_different_resource_Max_unitptime.pdf
We level resource quantity as leveling effor under partial workloads is unreliable. We disclose both, quantity and effort.
Good Luck
Member for
21 years 7 monthsBen,I used P6 years ago but
Ben,
I used P6 years ago but not any longer. If I am not wrong you specify individual values on the resource assignments tab. Make sure you make visible the column on the assignments tab so that you can edit the value.
If you are looking to control maximum available units at the project level as well as the global level then a workaround might be to create a dummy resource with the desired maximum at the job level. Then assign the dummy resource the same quantity to every team the global resource is assigned.
Good Luck.
Member for
8 years 1 monthBen,I would add a separate
Ben,
I would add a separate resource with a location identifier then allocate the Max Units/Time that way - e.g. Mechanic-Platform, Mechanic-Barge.
This will also allow you to set different calendars if required, which would also allow you the option of having a different calendar for the barge / work boat to take weather delay's into account.
Each project can then be scheduled independantly, or you can create a stacked histogram to see the combined resource hours for the same trade (or select the multiple trades in the resource profile).
This also allows you to identify the number of personnel on each site (for POB allocation if Offshore), as this is usually the limiting factor in the schedule. Again, the resource profile view will help with this.
We use Primavera EPPM for multiple assets offshore & all resources are set up with a location identifier to allow for the change in Units/Time.
If going this route, it is best to set up a Parent Resource of the Location to allow all the Site Specific resources to be added with the location as the Parent Resource - makes it easier when assigning in the plan.
If you are going to have to change the resource codes that are assigned on each location, then use a global change for each project / location to set the new Resource Code.
If you are using the Resource Leveling within Primavera, then you can then select only the resources you want to be leveled.
Steven