how to change max.time/unil 100% to h/d

1 reply [Last post]
Shazia khan
User offline. Last seen 12 years 10 weeks ago. Offline
Joined: 21 Apr 2008
Posts: 139
Hi All

Could any one advise in P6 how to change resource column max.unit/time it is showing 100% i want h/d

Thanks

Replies

Rodel Marasigan
User offline. Last seen 11 hours 1 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Hi Shazia,

Edit-> User Preferences-> Time Unit tab-> under Unit/ Time format change from show percentage to show as units/duration