unit/time

3 replies [Last post]
Sunil Babu
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Hi friends,

I want to change resource unit/time into decimal. In my system default value 1 is coming

how can I change to 0.3 etc..

Regads,

Sunil.

Replies

Sunil Babu
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 8 Nov 2010
Posts: 156

Arend,

Your answer was not enough for my question. Can you please explain the steps, in the resource  view

how can I change the default uni/time value..?Adding budgeted qty is defferent matter.

Regards

Sunil.

Arend Woltjer
User offline. Last seen 8 years 23 weeks ago. Offline
Joined: 26 Sep 2011
Posts: 74
Groups: None

Hi Sunil,

you can change the  Default units per time   in the resource view of P6, you have to enter a komma ( , )

When you add a resource to an activity you can change the Budgetted Units. The Budgetted units per time change automaticly then.

 

I hope this answers your question.

 

Regards,

Arend

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

what software?