In OPP for some reasn the Schedule Finish Dates are not matching the Actual Finish Dates. Activity is progressed and completed. Actual Finish Date is filled out and the task marked as Complete. There is 0 Remaining Effort. When I move the Time Now date forward, the Schedule Finish Dates move with it (Actual Finish Date stays the same). This is posing a problem since I have calculated fields that are based on the Scheduled Finish Column.