Assignment Challenges with MS Project..A few more tips

2 replies [Last post]
Seyma ISBLN
User offline. Last seen 10 years 32 weeks ago. Offline
Joined: 27 Apr 2010
Posts: 6
Groups: None
Hi again,

Really in toruble with my overdue uni assignment..I would appreciate the help guys.

When I assign equipments(crane, excavator) to the project (From assign resources) it changes the project completion date

It is the same problem when I assign a regular meeting as well.

What can I do to keep the project duration same and change the project cost only when I add these cost into the project?

Thanks heaps

Seyma

Replies

Seyma ISBLN
User offline. Last seen 10 years 32 weeks ago. Offline
Joined: 27 Apr 2010
Posts: 6
Groups: None
Thanks for the help Rodel.Much appreciated!
Rodel Marasigan
User offline. Last seen 3 days 33 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Seyma,
Right click and select task information or double click the activity. Click Advance tab and un-tick effort driven before adding new resource and your duration should not move.