Really in toruble with my overdue uni assignment..I would appreciate the help guys.
When I assign equipments(crane, excavator) to the project (From assign resources) it changes the project completion date
It is the same problem when I assign a regular meeting as well.
What can I do to keep the project duration same and change the project cost only when I add these cost into the project?
Thanks heaps
Seyma