Sorting tasks: some challenge there is !

1 reply [Last post]
Nicolas Igersheim
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
Hi all,

I have this model programme featuring typical
tasks and relations.
Unfortunately, tasks are sorted, and subsequently
numbered, according to ressource and not to logic
ie chronology.

I tried to create a new file copying
the tasks after sorting them according
to start date, thus relating number and chronology,
but unfortunately, when I do that,
the successors and predecessors numbers
refer to the copied tasks old numbers
and not the new pasted ones!

Any suggestion out there please?

Replies

Nicolas Igersheim
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
Well I should have looked
before I asked.
In the dialog box for Project Sort,
there is a check for
renumber all activities,
It seems to answer my problem all right.

Thanks anyway! ;-)