Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Recurring Milestones - Progress?

2 replies [Last post]
Philip Kearney
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 26 Feb 2002
Posts: 19
Groups: None
Currently masterplanning a major manufacturing project in Dublin at the moment.
Client wants his programme in MS Project so I decided to do the planning in a master plan format with the programmes broken into areas which are all linked back into 1 master plan using a milestone summary at the top so I can filter out the "works" to report using the milestone summary to show progress.

I also included a series of recurring milestones for commercial aspects of the project which are linked to some of the "technical/engineering" aspects of the project.

Thats all fine & dandy until I find out that my summary of the recurring milestones is not giving me a % of what is progressed as it stays at 0% when it should be at 40% ie 10 recurring milestones with 4 completed hence 40% complete but yet the summary tells me 0%???!!!!

Anyone here have any idea to get around this as it bothers me & I find it embarrassing to show on my report where my client expects to see % progress & notices the summary at 0%!

I understand that milestones are either 0 or 100% as have no physical value to them but surely after a series of milestones, there should be some form of period progression showing?

Replies

Philip Kearney
User offline. Last seen 3 years 38 weeks ago. Offline
Joined: 26 Feb 2002
Posts: 19
Groups: None
Thanks for replying!
I have given up hope on these recurring activities! Not gonna use them again as they do no purpose for progress!
Microsoft, take note please!
Yes, my s-curve is generated in excel & it show its worth.
What I have done is, took out the recurring activities as it was giving me grief & replaced it with a number of independent 1 day task but marked as milestones so it can be recorded at whatever % I will deem it at.
Anoon Iimos
User offline. Last seen 2 years 16 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
i suggest you do it in excel, you can put formula and never go wrong (at least in Math).