Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project 2007 changes my 2003 durations??

1 reply [Last post]
Mark Wells
User offline. Last seen 18 years 32 weeks ago. Offline
Joined: 4 Nov 2006
Posts: 7
Groups: None
I’ve just installed MSproject 2007 which I got because of the unlimited undo’s feature.

I opened a project in Microsoft Office Project 2007 that I created in Microsoft Office Project 2003 and started to edit it. I deleted an existing task and the durations of a number of other tasks changed, even though I didn’t make any changes that would affect their duration.

I should explain that this happens only tasks where I have:

A fixed duration constraint
A number of days duration (in this case 14)
0 hrs work
A cost entered in the cost column (in this case £500)

I set these tasks up like this to represent jobs which where being carried out by a 3rd party. In this example our supplier had quoted 14 days to carry out the job and given a cost of £500. I assigned 0 hrs work to the task because I don’t know how many working hours the supplier will actually spend working on my job but I do know the job will be ready to collect after a 14 day time period and want this to show on the project schedule.

2007 won’t let me set the task at 14 days duration and leave the work at 0 hours. Can anyone help???

Thank you

Regards
Mark

Replies

Mark Wells
User offline. Last seen 18 years 32 weeks ago. Offline
Joined: 4 Nov 2006
Posts: 7
Groups: None
MS have added a new resource type ’cost’ this appears to give the same affect as my work around. You create the task with a pounds cost in the cost column and duration and then assign the supplier (who you have set as a ’cost’ type resource) to the task and it automatically set the works hours to 0 (it even locks you out of the work column). Good Stuff!!!