Changing Fixed Units to Fixed Duration

1 reply [Last post]
John Pfluegler
User offline. Last seen 15 years 3 days ago. Offline
Joined: 3 May 2007
Posts: 5
Groups: None
I have inherited a ms project schedule which has all tasks set to fixed units & effort driven. The schedule has no resources and is purely used for forecasting based on durations.

Is there a way to change the activities which are in progress without the % complete & finish date changing?

Regards
John

Replies

Trevor Rabey
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Have you tried just selecting Tasks and using Task Information, Advanced?
What’s wrong with the way it is, or what is the reason for wanting to change it?
Since there are no resources assigned and no assignments being made, the Task Type and Effort Driven settings have no effect and make no difference and the % Complete and Finish Dates will not change.

Fixed Units and Effort Driven ON are the MSP defaults so it is no surprise that that’s how you get them.