Fixed duration, fixed units, fixed work, effort driven. How and why and when use all of it?

E
Evgeny Z. 👤 Member for 18 years 5 months

Dear all,

If I look at it, Microsoft Project effectively has 5 types of tasks (fixed duration, fixed units, fixed work. Plus each of them can be either effort driven or not effort driven, except fixed work, which is always efforts driven)

I  am using MS Project quite for a while, but I could never really understand, why Microsoft effectively has 5 types of tasks, why it is needed, and in which situation use one and not the other.  For my schedules I use most of the time fixed duration and sometimes fixed work.

Does anyone has a good guideline about this?

Regards.

Evgeny

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts