where is the switch to make % Complete change Remaining Durations? and vice versa

1 reply [Last post]
Rodney Jones
User offline. Last seen 3 weeks 6 days ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

Hello All,

where is the switch to make % Complete change Remaining Durations?

 

My Tasks are set as shown below, but the % Complete field seems to be manually entered, how do I get the % Complete to be auto calculated based on Remaining Duration or vice versa?

Replies

Paul Harris
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

In MSP the % Complete is always linked to the Durations and is calculated by the Actual Duration/Duration. It is not possible to cange the % Complete and only have the Remaining Duration change like P6.

Regatrds

Paul E Harris

Eastwood Harris Pty Ltd

www.eh.com.au