Manually changing remaing durations
Wed, 2012-08-08 10:03
Question: What is causing us to have to input six or seven times a remaining duration. Example: we want to show RD as 5 days, however, when we input, in comes up as 3.66. Then we put 5 days again and we get 3.97. This goes on until we finally get MP to show 5. Can anyone help us resolve this?
Wed, 2012-08-08 16:14
#1
try to check your default hours per day in Project Options. Your default setting should match with your project calendar.