Manually changing remaing durations

Question: What is causing us to have to input six or seven times a remaining duration. Example: we want to show RD as 5 days, however, when we input, in comes up as 3.66. Then we put 5 days again and we get 3.97. This goes on until we finally get MP to show 5. Can anyone help us resolve this?

H
Huzzle McNeive 👤 Member for 17 years 2 months

try to check your default hours per day in Project Options. Your default setting should match with your project calendar.