Progress Bars

1 reply [Last post]
Andrew Owenson
User offline. Last seen 16 years 4 days ago. Offline
Joined: 10 Nov 2005
Posts: 48
Groups: None
Guys

I am trying to incorporate two progress charts in one msp file. An active progress chart and a static progress chart. The active is the standard tracking gantt that comes with msp with an amended table to compare planned % against actual %. The static chart is easy if in a separate file - I baseline the project and change the activity bars to baseline start and finish, rather than start and finish. I then change the progress bar to Baseline start to complete throughout. If I record the actual starts and finishes in a dummy field ie start1 etc this works fine. However if i put this view in the same file as the active chart, the progress bar works but re-aligns itself to the actual starts and finishes, so sometimes the bar goes beyond the "planned" bar if behind programme or finishes before the "planned" bar if completed ahead of programme. What I want it to do is to stay within the baseline bar - any ideas


Andrew

Replies

Sukumaran Subaram...
User offline. Last seen 8 years 40 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
TRY : Progress Bar = Actual Start to Complete Through

Regards.