Costs against summary bars

1 reply [Last post]
Will Russell
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
I have a problem with the cost field in my plan.
There is a cost value against a summary bar but no costs against any of the tasks in that section of the plan. As its a "Cost" I cannot directly edit it.
There appears to be no logical reason why it should be there. There are no costs against any of the tasks or assignments and I cannot get rid of it!
Any advise or help would be greatly appreciated.

Will

Replies

Will Russell
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 9 Apr 2003
Posts: 48
Groups: None
Fortunately, I have found the answer to my own problem, but for the benefit of the group here is where the problem was - "Fixed Cost".
The Fixed Cost field is one of the fields that can be edited directly against a summary bar. So beware!!

Will