Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EOT for a Particular Section of the Road

2 replies [Last post]
Prageeth Chandrasiri
User offline. Last seen 6 years 38 weeks ago. Offline
Joined: 6 Jul 2011
Posts: 7
Groups: TILOS

Dear All,

I have a problem related to an EOT Claim. Our project is a 10 Km long Highway & there are no sectional project completion dates as per contract.

Currently, work is in progress but behind the schedule. Unfortunately, at the very end sections of the project, we encountered a Unforseen Physical obstruction. So that, now the Engineer is planning to grant a EOT for that particular section (0.50Km) only & has instructed to the contractor to complete the other works (9.50Km) as per contract.      

Please clarify whether this is inacordance with the contract or not

Thank You in advance.

Prageeth 

Replies

Prageeth Chandrasiri
User offline. Last seen 6 years 38 weeks ago. Offline
Joined: 6 Jul 2011
Posts: 7
Groups: TILOS

Thanks Mike for responding to my query and to your valuable comments.

Mike Testro
User offline. Last seen 6 weeks 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Prageeth

It depends what it says in your contract but a whole project cannot be split into sections for the sake of extensions of time.

What you have here is a concurrent delay situation where the contractor's late work is concurrent with excusable delays.

It may end up that you get your EoT for the Tie-ins but no delay related costs.

It may be that the Engineer is trying to achieve this result but in a roundabout way.

You will need to establish the direct cause and effect of each head of delay on the completion date and then set out your concurrency case.

Best regards

Mike Testro