Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Total float issues

3 replies [Last post]
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi

I checked the ownership of total float in the specification

It has been defined as

Ownership of float belongs to the project {who ever use it first} .

what does who ever use it first mean ?

Replies

Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Thanks Samer and Gary
Samer Zawaydeh
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Shahul,

There are many articles about the subject. What you described is only one opinion "Whoever use it first".

IMHO you need to look at it case by case. The Schedule is prepared by the Contractor. The client doesn’t need the schedule, they need the end product. Schedules are tools to solve the issues. Expert opinion at site is a better way to solve the issues. Especially from the people who have hands on the issues.

With kind regards,

Samer
Gary Whitehead
User offline. Last seen 6 years 1 week ago. Offline
It means the first delay events to occur will not result in EOT regardless of whether it is contractor or client responsibility, up until the point when all total float is eroded.

Regards,

Gary