Calendars in Programming

2 replies [Last post]
Lo Gary
User offline. Last seen 37 weeks 6 days ago. Offline
Joined: 7 Feb 2010
Posts: 52
Groups: None
Supposing the project duration is 300 calendar days and I use calendar with public holidays and weekend (assuming a 6 days work week) for scheduling of construction activities.
I scheduled to have a pour of concrete on this coming Saturday, but the consultant suddenly revised the drawings and the concreting had to be postponed 2 weeks later. Do i entitle the EOT on the Sundays or public holidays?


Gary

Replies

Mike Testro
User offline. Last seen 27 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Gary or Lo

The result of an impacted delay event depends entirely on the quality and detail of your programme.

Can you see precisely in your programme where the delayed pour sits - or are you guessing where it might be in a more global programme?

If it is the latter then you will have great difficulty demonstarting any cause and effect.

I await your response with interest because this goes to the nub of my crusade regarding Bottom Up FS programming.

Best regards

Mike Testro
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Gary

You can mark change in design as delay event and impact it on your programme, by the way which cause and effect method you employ for the demonstration of extension of time?.After the impact check do they have any impact on your project completion date.If yes then variance of project completion date of impacted programme and Consented/Updated programme project date in calender dates is your entitlement