If need to evaluate the impact of delay event whereas, the contractual programme's calendar is a 6 working day, what calendar to be used in the relevant schedule which is to be used to produce the Impacted Schedule, do I have to change the contractual programme calendar into (7 working day calendar) or the Impacted schedule shall preserve the contractual 6 working day calendar?
Calendar to be used for evaluating the impact of delay event
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hi Amar
28 calendar days.
Best regards
Mike Testro
Thanks a lot Mike,
Just to make sure that I've understood you correctly; say I have the following situation:
Thanks again
Ammar
Hi Ammar
Retain the working calendar for the impacted tasks.
The shift of the end date demonstrating delay should be represented by a hammock which has a 24/7 calendar.
The impacted events in the fragnet may have different calendars as required.
Best regards
Mike Testro