Your suggesstion is most required -All about TIA

8 replies [Last post]
Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773

1-I had a delay event named availability of construction drawings form consultant right from project start date in this case? how do we use TIA since no updates available at the moment of project start.

Replies

Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
I mean to say introduction of delay event fragnet on planned program which looks similar to impacted as planned method ?
Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
hi to all

if delay event is on first day of project start date then no updates available since project has just commenced .In this TIA looks like impacted as planned method is it correct?
A D
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Shahul,

If u show only one bar, then it may not solve the pupose.

This activity is linked with may be 100+ other activties. So, to demonstrate the impact you need to split this activity into different set of drawing activities and so, the impact of this on succeeding activities and on the project completion. If the start and end date of hammock activities remain same, and u insert few new activities, will give u a clear picture of the entire series of delay events.

While preparing a claim program, make sure that even ur site team will understand it and shud not remain a piece of paper from planner.

Cheers,
Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Shahul

Put in a big red activity bar called Late Issue of Drawings.

Make it start from the day 1 and link it FS to the 1st activity that needs the drawings.

Make the end date Monday 16th November and re schedule.

Every week make the bar 1 week longer until you get the drawings.

Best regards

Mike Testro
Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Mike

Right from day 1 indicative design been issued and contractors are working on it after 6 months consultant revealed that whole design got changed and they gave set of drawings {construction} .Asked contractor to proceed from the start of it again.
Please advise how to proceed in TIA
Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many thanks Mike .

Mike Testro
User offline. Last seen 5 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Shahul

How much actual work had been done following the wrong design?

If none then the TIA will be a bar between date of issue of wrong drawings to date of re-issue drawings with the same FS links in place.

This will demonstrate the likely completion of the project and the EoT.

If some work had been constructed then it may have to be replaced so demolition / break out work may need to be added.

This would be concurrent with the new design development / workshop drawings lead in for new construction.

The contractor will be entitled to be paid for all abortive design and construction work.

Best regards

Mike Testro
Shah. HB
User offline. Last seen 19 weeks 2 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Thanks to all

On submission of delay event 1 TIA to consultant could we link event 1 with upcoming delay event 2 [ which is under preparation stage]