Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

acceptance, consent, approval and agreement of programm

29 replies [Last post]
Amr Elserafy
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 8 Jul 2004
Posts: 18
Groups: GPC Qatar
Hi all,

would anybody please tell me the difference between acceptance, consent, approval and agreement of programmes.

Regards

Amr El-Serafy

Replies

Oscar Wilde
User offline. Last seen 16 years 9 weeks ago. Offline
Joined: 7 Oct 2005
Posts: 166
Groups: None
Its interesting that it is widely held in this thread that the programme is approved.

Since a rather nasty accident in the UK where a method statement was approved by a consultant and life was lost due to what the judge felt to be basic science and in turn the consultant was held partially liable, consultants have, where english law is the basis of the countries law abbrogated the responsibility for approval.

Simply put very little is now approved by Consultants, often the highest level of "approval" is no comment at this time.

or follow comments no need to resubmit

clearly if your engineer wants you to increase float i assume that this is probably on his approval activities or information provision activities. Resist the tempatation if he has no authority under the contract to make such a request. Follow what Mr Ness has said about the claims if he insists.

I would be very interested where programmes are still being formally approved.
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello Joe,

You programme is good as approve. The only outstanding item is the issue with regards to float.

Check again the programme if there is really another logic to arrive with increase float.

Be careful with this exercise considering that "who own the float" is still a subjective question.

Cheers
Charlie
Stuart Ness
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
Joe,

I sympathise with anyone having to deal with a capricious Engineer!

As Jose says, I would stick to the wording in the Contract. Or at least as much as you can

If your Contract has the usual 3 options that Jose refers to, then your status would appear to be ‘approved with comments.’

If – as is more likely – your Contract is silent on the matter, I think that the same principle would apply; in other words, he has approved the programme, but only if you carry out certain modifications to it, and – by extension – he is unlikely to grant approval until you comply with his comments.

Of course, you may argue that his ‘comments’ are unrealistic, particulary where they are inconsistent with the Contract documentation, such as the Specification. In this case, get him to commit his comments (including his ‘conditional’ approval) to paper, so that you then have a basis to claim (or at least protect yourself) at a later stage in the event that things begin to unravel!!

If the Consultant refuses to commit his ‘conditional consent’ to paper, it’s a sure sign that he knows within himself that he is on shaky ground. If he does not commit his requirements to paper (particulrly if these requirements are contrary to the Contract), then you have no written instruction and you have no need to comply with his ‘requirements’.
Alternatively, you can confirm his verbal instruction and proceed on that basis, but give notice of your intention to submit a Change/Variation Order for additional time and/or costs on the basis of his insruction, if this is appropriate.

One other question: does the Engineer have to approve the Programme within a given time frame? If so, and if he has not commented on it within the due time frame, then your Programme may be deemed to have been approved in any event.

Hope this helps,

Cheers,

Stuart

www.rosmartin.com
Edgar Ariete
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184

Hi there,

How about acceptance by simple TRUST?
Jose Frade
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 7 Jun 2005
Posts: 144
Groups: None
Hi Joe

Normaly the approvals/comments must follow what is writen in the contract:
Very often:
1. Approved
2. Approved w/ comments
3. Not approved.

You should stick to the contract.

Increasing the float ? your contract works program does not have a critical path ?

Under such circunstancies it would mean to perform shorter then contractualy agreed (immediately would be cause for claiming acceleration costs / shortening period / etc)

Best regards
JMFrade
Joe Mansour
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 10 Sep 2002
Posts: 46
Groups: None
Hi all,
I am facing a case where the Consultant has given a "conditional consent", with reservations that are not required in the specifications, especially with regard to increasing the float.

My reply was that I consider a "conditional consent" as "no consent", as the contract does not allow for "conditional consent", and that the consultant’s authority in checking the programme does not extend to imposing conditions on the float.
He considers that the contract does not also state that there is no "conditional consent".

I would be interested in some experts opinions on the subject.
Regars
Joe
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Andrew,

I agree with you 100 percent.

At least it gave us confidence that irrespective of the politics within the project management team, we planners will do our job: prepare baseline schedule and monitor the progress of baseline schedule.

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Charleston,

Precedence - virtually every case that ever existed!!!!!!

Approved or not, the programme submitted 99.9% of the time is the only record and is therefore the only available evidence of the contractors intentions in regard of time, sequence, etc. Therefore it is used what ever it’s status.

An unapproved programme will probably cause more arguements to be put forward but it will still be used as evidence.

It’s actually a much bigger problem if no programme at all has been submitted!!
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi,

Alex, I agree with you regarding the statement "baseline schedule ... reaches the Approved/Agreed with comments stage". At this phase the comments are minor and will not have any impact to the schedule. Generally, this is good as aprroval of the schedule.

Andrew comment "the agreed program is always taken (and normally is) the contractors intended sequence of work..." is interesting. This maybe true but on what basis in Contract Law that the statement is correct or got precedents considering that the other party of the contract did not approve/agree but only commented on the submitted/re-submitted schedule.




Alex Wong
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Charleston-Joseph

The scenario seems very familiar to me. My answer is baseline schedule should be use for analysis is when the resubmitted schedule first reaches the Approved/Agreed with comments stages. Because if the Clients Rep keep on having new comments that means that they(Clients) did not completed their initial review properly that means they did not carry out their duty in accordance with the contract. Therefore, it is not the contractor responsibility to continuously accommodate the clients new requirement each time. Unless the new comments is base on schedule impacted by the original comments or schedule changes by the contractor.

That’s what the case I was working on few years ago.

Alex
Alex
Amr Elserafy
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 8 Jul 2004
Posts: 18
Groups: GPC Qatar
Dear Planner Planner,

i think what we should do i strying to be fair all the time. It is true that sometimes you might face situations like that, but at the end of the day there is a contract to be respected through your system whatever it is. In my opinion that you should tell your company the fact and it is due to your decision maker to take the sequences. Doyou agree with me, or you have other ideas. I will be glad to hear it.

Cheers

Amr
X Planner
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
B.T.W

i fogot to tell,

it ended up without applying any delay fine on the subcontractor.

cheers,
X Planner
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None


that what makes our job most difficult,
u feel confused about being fair if that will put u against the contract terms which means against ur company.

because ur company hired u to protect them as much as u can. ( not to be fair-their point of view) .

i had a similar situation once when the subcontractor was pretty sure that there will be no penalties or delay fine applied upon him by the end of the project ,
and i’m sure that all of u guys now can imagine what was the impact of this on his performance during the life time.
the project ended up 5 months after the contractual finish date.

so which way would u rather to go through during the project life time, the contract or the system set out by ur company?

Regards,
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Amr,

Pretty hard for anyone in the company to fault you if you do.
Amr Elserafy
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 8 Jul 2004
Posts: 18
Groups: GPC Qatar
Dear All,

thanks for your comments, but nobody mentioned anything about Consent.

I believe that using the system set out by the company regardless by the wording is the most wise thing, don’t you agree?

Cheers

Amr El-Serafy
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Planner,

The agreed programme is always taken as (and normally is) the contractors intended sequence of work and progress etc monitored using it. As it is the normally the only evidence available of the contractors intentions, it will always be used as the baseline for considering eot’s and similar.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Charleston,

The start, finish, sectional completion dates are contractual and are directly taken from the contract documentation. The program is an indication as to how the contractor intends to build the project, but only an indication. Within the contract dates the contractor is usaully free to build the works however and in what ever sequence he wants as long as he complies with the contractual dates. This in effect is recognising the contractors right to manage the works as he wishes subject to the constraints of the contract. The programme therefore is not an actual contract document unless expressly included.
X Planner
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
i think that we need a specific answer to that general question:

does updating that program and using the %’s of completion for measurement or directing letters for the contractor or highlighting them in the progress meetings considered as an approval for the baseline????

is it yes or no?
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Andrew,

I beg to differ with your statement “the reason the program is not made a contract document is actually to protect the client …”

There is always a plan or program in all organization. Planning is a function of management. In project management, planning is the most important function since the inherent nature of project management makes it mandatory to have a plan, to have a start and finish of project, to have a program or plan of action on how to start and finish the project

It is for the interest of the client to have a start date and finish date in all projects. Generally, the client incorporated the start and finish date in the contract. The client did have a program to start and finish the projects.

We have to agree that for a project to be successful, a plan or program must be in place. A baseline schedule must be in place to monitor the progress and to know where the project is heading. The project manager including the project management team may act irresponsibly, play politics, derelict in their duties or loss touch with their management training and belief, etc. by not approving a baseline schedule, but we planners must be strong and find ways to have a baseline schedule. This is the only way to insulate us planners from the dirty politics of project management to do our job as planners and produce all our deliverables.

The issue at hand is how the baseline schedule will become a contract document considering that there was no approval of baseline schedule. There must be some court rulings that establish precedent on how the submitted and commented but not approved schedule becomes an approved schedule without the word “approve” and part of the contract document.
Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
All,

In general - the programme is not usually a contract document unless expressly made so by the contract. The contractor has the right to carry out the work as he see’s fit as long as he meets all the contractual completion dates - sectional and/or final.

It’s approval by the engineer, and there’s often a clause stating this, does not relieve the contractor of any obligations nor attach any to the engineer.

The reason the programme is not made a contract document is actually to protect the client as it is argued that if it were so, ANY delay to ANY part of the programme by the client could lead to damages being due.
X Planner
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
charlestong-joseph, is correct but the conclusion is:
The client never issue a letter of acceptance of the contractor’s submitted program but as u said they use it as a baseline during the construction and they update this program for monitoring and performance measurement purposes.

The point here is, Updating that program and using the %’s of completion for measurement or directing letters for the contractor or highlighting them in the progress meetings is not considered as an approval for the baseline????

Bill Guthrie
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
Thanks Ron, appreciate your update, the case I was referring to was over 7 years ago, times changes everything
especially Court Cases in the states.

cheers Bill
Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello,

Every project is unique. Let us consider this kind of scenario. The contractor submitted a document (schedule) and the client acknowledge receive of the schedule. The client did not approve the schedule. The client also did not reject the schedule but commented on the schedule for resubmission for the contractor to incorporate the client’s comment. The process of submission and re-submission continue during the concurrency of construction activities. The contractor was able to comply with the comment made by the client however the client was also able to come up with new and reasonable comments every time the schedule was submitted for approval. During the progress of the work, the contractor and the client used the submitted but commented schedule. All performance evaluation and monitoring of progress including updating, look ahead, etc was based on the submitted schedule.

For case study purposes, the project was delayed and the contractor file for EOT, claims, entitlement, etc. Due to complexity, the contractor will hire a forensic analyst/claims specialist. One of the forensic/claims specialist activities is to prepare an impacted schedule showing the events, instruction, etc and how it affects the work schedule. But now the question is which baseline schedule to use.

As planner, it is very frustrating to get stuck up in this kind of project management environment. It is for this reason between planners (contractor and client) it is very important to arrive at an approved schedule as early as possible. In this way a baseline schedule must be agreed and put in place for the project management team to monitor and compare progress.

Raja Izat Raja Ib...
User offline. Last seen 12 years 47 weeks ago. Offline
Joined: 2 Jun 2005
Posts: 299
Hi Suku,
As far i know,
1.In Contract there is a clause stated for planning activities and they will attached planning package (CPN, Schedule,Manpower Hitogram, S-Curve) and planning procedure as approved schedule.
2.For changes in design they will put as Change Order, but if the scope is not included in contract they will do as VO=Variation Order. EOT only for any additonal works such as VO and Resonable Delay.
3.Depends with the contract.
Sukumaran Subaram...
User offline. Last seen 8 years 39 weeks ago. Offline
Joined: 2 Mar 2005
Posts: 229
Groups: GPC Malaysia
The contractor prepares the schedule and submits to client/consultants for review and approval. The client/consultants accept, review and keep for record the schedule but remain silent on approval. Can the schedule become a contract binding document?

Since the schedule is not approved and only accepted for record, does the contractor solely responsible for any changes occurred during the construction period i.e. changes in design. If construction work is delayed due to the design changes can contractor apply for EOT? If the changes is not major and client/consultants assume it can be absorbed in the construction period definitely contractor won’t be happy because of loss time.

Client/consultants and contractor can involve in lengthy argument and let say both parties bring the case to arbitration but if the schedule as a part of the contract document is not approved does it valid in court. How to justify the validity?

What we need to emphasis here is does the acceptance for record by client/consultants can be considered as approval or not.

Regards.
Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Bill,

Just because a Contractor claims that you assumed responsibility due to your approval does not make it so. USA courts have consistently ruled that the verbiage contained in the acceptance is immaterial.

Go ahead and use your company-meditated word if you like, but the courts have ruled that the creator of the design is responsible for that design. The Owner only reviews the submittal for compliance with the plans and specifications. The review may also cover compliance with other aspects, but the Owner is not responsible for catching all mistakes made and codes violated. That is the designer’s responsibility.

Good luck!
Bill Guthrie
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
And sorry, forgot to run spell check

bill
Bill Guthrie
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 14 Mar 2005
Posts: 262
WhaT YOU HAVE TO TAKE CARE ON

IS.

When you are the client, and you "APPROVE, OR ACCEPT " a schedule you could be taking responsibility for it. Same as with Engineering deliverables.

Several years back, when working for a major, the contractor became pissed at us and filed a claim because we apprived the detailed design,and it was wrong. When we tried to recover from the contractor, he said We had responsibility because we approved. Get my point? And another contractor wammied us because we did not approved
the drawings, thus he was not responsible.

As a result, from that day on, the Major Oil company NEVER again used the verbage Approve on drawings, etc.

The contractors are responsible for his design, so he has to check the drawings,specs to see of correct, not client.
Client from that point on only should review and audit design only, letting the responsibility for each drawing correctness remaining with the contractor.

And relative to Schedules,etc, client should review and state he has no objection to Contractor using a certain schedule or program, Never approve or disapprove.

A word game but one that we must really take care with.

Hope this helps
bill

X Planner
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 17 Jun 2002
Posts: 78
Groups: None
nothing...