Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

’penalties’ in sub-contract agreements

10 replies [Last post]
Milind Pandhare
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
Guys I have a general Question

Should you apply ’penalties’ in sub-contract agreements and why/why not?

Replies

A D
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi Milind,

Coming back to ur question:

1. Is it required to have LD Clause in ur sub-contractors contract.
- At some point, the project may not go as planned. For some reason, project will not finish as it was designed and neither within budget. Despite best efforts, the original schedules become a thing of distant memory. If u r in this situation before, u know very well that it doesn’t take much time to start the blame game and everyone starts pointing finger and then starts the damage claim related to delays. The solution to some of these delays is inclusion of Liquidated damages in the contract.

2. Purpose of LD:

-LD can only remove SOME of the uncertainty related to construction delay claims and NOT all. But, definitely its a good weapon to make sure project completes on time.

To be valid, a LD clause must satisy a two-part test. First, the damages covered by the clause should be incapable or difficult to estimate at the time of the contracting. Second, the liquidated amount must be a reasonable calculation of expected damages. The key is taht a liquidated damages must not be a penalty.
Milind Pandhare
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
I think it is Head office administrative expenses

http://main.constructionreviewonline.com/CONTRACT%20CLAIMS%20-%20BY%20JO...
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Scarllet,

Where did you come across the term "Administrative Charge" please? Under what form of Conditions of Contract

With kind regards,

Samer
Scarllet Pimpernel
User offline. Last seen 12 years 43 weeks ago. Offline
Joined: 19 Jul 2009
Posts: 152
Dear Milind,

In some cases, penalty is a harsh word.

Client usually treat the Contractor as partner since without the contractor or sub contractor, no way can a client do the project.

So, my idea only, it is preferable to use the word "Administrative Charge".

Thank you,
Scarlett
A D
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi Milind,

Try this: By Quenten Fleming
http://rapidshare.com/files/263005538/jk27.rar

Good review on websites (Never purchased or downloaded by me though).

Give a try.
Milind Pandhare
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
Thanks
Sameer .
for your valuable Comment .
Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
In Australia, and probably in other places, the word "penalty" is never used in contracts and the reason is that they are un-enforcable.
The law generally has no regard for enforcing penalties, which can be arbitrary amounts, but is more supportive of awarding damages which are a realistic approximation of the actual damage. So when there is a reference to LDs there is always or usually a statement to the effect that the parties agree that the amount represents a reasonable assessment of damages and specifically is not a "penalty".
Samer Zawaydeh
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Milind,

"It Depends". Penalties are a standard condition of Contract. What Gary is suggesting is very practical and you are adviced to follow. Whatever penalties or terms of payment you have, carry it over to your subcontractor.

On the same note, the main contractor can not afford the losses that might be incurred because of the subcontractor. That is why, the answer to your question is "It Depends".

If the Main Contractor has a strong management team, then they will replace the subcontractor at the first sign of major failure, or even before that. If the subcontract value is small, then the amount of penalties would be small, but the amount of penalties on the main contract because of delay would be large. Hence, you need to negotiate a balanced contract with the understanding that the common goal is to deliver the complete scope by all parties.

With the proper experience, you can make sure that you have a good Balanced Contract with your subcontractor.

With kind regards,

Samer
Milind Pandhare
User offline. Last seen 8 years 7 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None
Gary if subcon is nominated then no prob
if i have inhouse sucontractor .Should i impose a penalties clause while subcontracting with him.if he dalay for certain duration wich cause delay in Project Finish Date.As a contractor we will get penalise By client with certain cost at the max 10% .But its a pure delay by subcon though his contractul Sum is @20% of the contract he will be penalise max 10%of his contract sum wich is more or less 2% of the project cost .And if the penality is up to 10%of the project cost who will bear the 8% ...
Gary Whitehead
User offline. Last seen 4 years 47 weeks ago. Offline
Generally speaking, I would say a contractor should try and mirror the penalties in his client contract with his sub-contracts.
That way the risk of penalties is taken by those most responsible for incurring them.