Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Float Path Analysis

4 replies [Last post]
Chris Wilson
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 21 Oct 2016
Posts: 16
Groups: None

Hi,

I am looking to view the first 5-10 critical paths to help manage a project where more and more activities are losing their float, but cant find a way of doing this easily in Asta.

Obviously the critical path is quite easy to see but the next logical path  behind it thatsay may have 1-2 days float in it is hard to find.

I have looked at using the logic path filter and numbering however these are not great as for instance if a milestone is constrained early then this is shown as a critical path which means the actual critical path  is not shown as logic path 1. It also seems to split at differing stages.

Any help would be appreciated.
 

Chris

Replies

Chris Wilson
User offline. Last seen 8 weeks 2 days ago. Offline
Joined: 21 Oct 2016
Posts: 16
Groups: None

Thanks Mike, but its a lenghty programme with  a large number of different float paths. I was hoping to be able to provide full float paths from start to finish so that they could be prioritised. If I filter by total float and copy into a spreadsheet I risk losing the logic and if two float paths have the same total float it wont differentiate between them 

Rafael Davila
User offline. Last seen 1 hour 37 min ago. Offline
Joined: 1 Mar 2004
Posts: 4784

That many scheduling “experts” insist on longest path when it breaks for resource leveled schedules is beyond comprehension.  I do not understand why an activity that belongs to the longest path is more critical than another activity that do not belong to the longest path but have smaller total float. The float path values do not represent a ranked order of criticality.

ORACLE what are Critical Path Activities?

  • The longest path is broken when activities are no longer driven by relationships; that is, when activity dates are driven by constraints or resource leveling. Longest path calculation includes interproject relationships. Therefore, activities designated as on the longest path may change depending on whether you schedule a project alone or with its related projects. If a project has interproject relationships and you schedule it alone, the interproject relationships are treated as scheduling constraints.

With resource, financial, supply, space constraints the existing Longest Path theory does not work.

Total floats are useful and sufficient for understanding what activities require maximal attention.

Mike Testro
User offline. Last seen 1 week 9 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4395

Hi Chris

You can filter on Near Critcal tasks by deducting days from the total float.

Just deduct days from the total float and copy paste the results to a spreadheet

Best regards

Mike Testro

Ben Taunt
User offline. Last seen 1 week 3 days ago. Offline
Joined: 16 Jan 2012
Posts: 93
Groups: None

Hi Chris,

Is there anything in the Help Files that assists?

http://help.elecosoft.com/powerproject/english/15.0.01/Content/Search.ht...

If not, this sounds like a question for our support team so that they can discuss with you exactly what you're looking to acheive.

Cheers,

Ben @ Powerproject