Critical Path - Help Needed

2 replies [Last post]
Dominic Planner
User offline. Last seen 25 weeks 2 hours ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Good Morning, 

I'm having issues establishing the Critical Path on my programme. I have a summary section at the top of my programme with Key Dates i.e. contract award, mobilisation, construction period, handover etc. 

The Critical Path seems to bypass my entire programme and only link these activities as critical. The only 'Critical' items on the main programme is the start milestone and completion milestone. 

Any help to get round this woul be appreciated. 

Thanks 

Replies

Dominic Planner
User offline. Last seen 25 weeks 2 hours ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Alexandre, 

 

Thanks for your help, I managed to correct it. 

Dominic