Hi,
I am looking to view the first 5-10 critical paths to help manage a project where more and more activities are losing their float, but cant find a way of doing this easily in Asta.
Obviously the critical path is quite easy to see but the next logical path behind it thatsay may have 1-2 days float in it is hard to find.
I have looked at using the logic path filter and numbering however these are not great as for instance if a milestone is constrained early then this is shown as a critical path which means the actual critical path is not shown as logic path 1. It also seems to split at differing stages.
Any help would be appreciated.
Chris