Lags and type of duration format

1 reply [Last post]
Farhad Khondaker
User offline. Last seen 3 years 22 weeks ago. Offline
Joined: 30 Sep 2014
Posts: 11
Groups: GPC Malaysia

Hi All,

Please can you advise on the following-

My programme activities are showing incosistent time units on my lags and slope. The activities are showing a mixture of seconds, minutes, hours and days on my activities.

Is there a way i can select a consistent format for all activities to have their lags calculated in days, weeks?

Thank you in advance.

 

Regards,

Farhad

Replies

Mike Testro
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Farhad

In the column you can format the duration by the Format Cells dropdown.

You can do the same by selectiong the link and change the suffix ie 15w or 15d.

As a general rule you should only use lead lags for curing or drying out periods and then it should be set as calendar days - 15ed.

Best regards

Mike Testro